"Oh Sheet!" – The Importance Of Detailed Time Sheets In Proving Quantum Of Damages

In Sjostrom Sheet Metal Ltd. v. Geo A. Kelson Company Limited, 2023 ONSC 4959, the Ontario Superior Court of Justice affirmed several key legal principles, including the importance of carefully drafted pleadings.

CanadaReal Estate and Construction

In Sjostrom Sheet Metal Ltd. v. Geo A. Kelson Company Limited, 2023 ONSC 4959, the Ontario Superior Court of Justice affirmed several key legal principles, including the importance of carefully drafted pleadings, the validity of oral contracts, the significance of good record-keeping in quantifying damages, adherence to contractual default notice provisions, and the consequences that may flow from ambiguous or incomplete change orders.

This matter involved two actions arising out of a construction project whereby University Health Network ("UHN") hired Canadian Turner Construction Company Ltd. ("Turner") as the general contractor to build the UHN Centre for Cell & Vector Production ("CCVP") in Toronto. Turner subcontracted with Geo A. Kelson Company Limited ("Kelson") for the mechanical scope of work. Kelson further subcontracted with A. Amar and associates Ltd. ("Amar") to perform certain sheet metal work. Amar hired labourers from Sjostrom Sheet Metal Ltd.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from