The Ontario Superior Court of Justice ("ONSC") recently highlighted the importance of the summary nature of construction lien proceedings and confirmed that delay can constitute...

CanadaReal Estate and Construction

The Ontario Superior Court of Justice ("ONSC") recently highlighted the importance of the summary nature of construction lien proceedings and confirmed that delay can constitute a "proper ground" for dismissal of an action under section 47 of the Construction Lien Act ("CLA"). Nova Concrete Inc. v. 2035211 Ontario Inc., 2022 ONSC 2391 provides important guidance for parties to construction lien actions in Ontario, as well as insight into the inter-related nature of construction lien actions and breach of contract actions and the "intertwining threads" between the procedural rules governing construction lien actions and those governing ordinary civil actions in the province.

Facts

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.