Not All Work Will Extend The Lien Period

Bennett Jones LLP
Bennett Jones LLP
Contributor
Bennett Jones LLP

Bennett Jones LLP

Bennett Jones is one of Canada’s premier business law firms. With deep experience in complex...

View firm profile
Explore more from Bennett Jones LLP

Contractors, subcontractors, suppliers and labourers in Alberta typically have only 60 days after completing the last work on a project to register a construction lien.

CanadaReal Estate and Construction

Contractors, subcontractors, suppliers and labourers in Alberta typically have only 60 days after completing the last work on a project to register a construction lien. This period is extended to 90 days for concrete work and work on an oil or gas well site.

The Alberta Court of King's Bench recently reaffirmed in Phoenix Treatment Systems Ltd v 1924613 Alberta Ltd, 2025 ABKB 714 (Phoenix Treatment Systems) that not all activities will qualify as lienable work capable of extending the 60- or 90-day deadline. As the plaintiff in Phoenix Treatment Systems discovered, misidentifying the last day when lienable work was performed can be fatal to an otherwise valid construction lien.

The Case

Phoenix Treatment Systems Ltd (Phoenix) completed plumbing work at the Grande Cache Mall on 22 May 2024, following a sewer backup. No written contract governed the engagement. On 3 June 2024, at the owner’s request, a Phoenix representative visited the site to explain the completed work to the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.