Milestone Payments And Proper Invoices Under The Prompt Payment And Construction Lien Act

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The PPCLA itself, however, does not appear to contain any such express requirement.

CanadaReal Estate and Construction

Background and Interpretation

Under section 32.1(6) of the Prompt Payment and Construction Lien Act (the PPCLA), "proper invoices" (as that term is defined in section 32.1(1)) are to be given to an owner at least every 31 days unless the contract includes a provision for the testing and commissioning of the improvement or of the work done or materials furnished under the contract and the conditions of testing and commissioning are not met.

This requirement does not appear to contemplate milestone payment schemes, which only require payment to be made by an owner (or a contractor, as the case may be) when agreed upon progress or objectives are met and which consequently, only require a contractor to submit its invoices to an owner upon meeting those objectives (as opposed to strictly following a monthly, bi-weekly or some other invoicing and payment system). Indeed, the 31 day requirement in the PPCLA does not contemplate any invoicing interval other than at a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from