Lien Everything, And Early: The BC Supreme Court Clarifies Builders Lien Filing Deadlines And Apportionment Between Properties

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

The recent decision of the British Columbia Supreme Court in Frontier Kemper Constructors, Inc v Rio Tinto Alcan Inc clarified the timeline for filing a builders lien when the 45-day...

CanadaReal Estate and Construction

The recent decision of the British Columbia Supreme Court in Frontier Kemper Constructors, Inc v Rio Tinto Alcan Inc1 clarified the timeline for filing a builders lien when the 45-day deadline falls on a weekend and revisits the limited scope afforded to the court under sections 24 and 25 of the British Columbia Builders Lien Act  (BLA).2

Background

Rio Tinto Alcan Inc. (“Rio Tinto”) brought an application for an order to cancel a $96 million claim of lien that was filed by Frontier Kemper Constructors, Inc. (“Frontier Kemper”) with respect to a tunnelling project for the Kemano power generating station owned by Rio Tinto. Some of the issues before the Court were:

  1. Whether the lien should be cancelled because it was filed out of time; and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from