ARTICLE · 23 SEPTEMBER 2024

Judicial Review Of Adjudicator's Determination Of "Contract Completion" Pursuant To The Construction Act

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The Ontario Divisional Court recently confirmed that "contract completion" is defined the same way for adjudication purposes as for all other purposes under the Construction Act (Ontario)...

CanadaReal Estate and Construction

The Ontario Divisional Court recently confirmed that "contract completion" is defined the same way for adjudication purposes as for all other purposes under the Construction Act (Ontario) and completion determined by reference to the value of uncompleted work and not the statement of accounts.

In Jamrik v 2688126 Ontario Inc. (2024 ONSC 2854), the Ontario Divisional Court released a decision which assessed an Adjudicator's determination of when a contract in dispute was deemed "completed" pursuant to sections 2(3) and 13.5(3) of the Construction Act. The Court found the following:

  1. The Adjudicator erred in making a finding on whether the contract was completed when submissions were not made on the issue.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.