How Long Is The Builders' Lien Registration Period For Drilling And/Or Servicing A Well Or Well Site On An Oil Sands Project? Spoiler Alert – It's 90 Days!

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

The Court of Queen's Bench of Alberta held that the 90-day lien period to register a lien against an "oil or gas well" or "oil or gas well site" applies to drilling on oil sands mines.

CanadaReal Estate and Construction

In the recent decision of Davidson Well Drilling Limited (Re), 2016 ABQB 416 ("Davidson") the Court of Queen's Bench of Alberta held that the 90-day lien period to register a lien against an "oil or gas well" or "oil or gas well site" applies to drilling on oil sands mines. The Court also concluded that the costs of trucking equipment away from a project site after it is completed may, in certain circumstances, be properly included in a builders' lien.

Under Section 41 of the Builders' Lien Act, RSA 2000 c B-7 ("BLA"), a lien for materials or the performance of services must, in almost every instance, be filed within the 45-day lien period starting from the day that the last of the materials or services are provided or the relevant contract is abandoned. The BLA does, however, provide a special exception respecting liens for improvements to an "oil or gas well" or "to an oil or gas well site", by extending the lien period to 90 days. As the terms  "oil or gas well"