Share on LinkedInShare on LinkedIn

ARTICLE · 24 OCTOBER 2025

Equitable Set-Off And Clean Hands: What Alberta's Latest Court Of Appeal Decision Means For Construction Claims

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

For construction law practitioners, this case provides useful guidance for when equitable set-off can serve as a valid defence to summary judgment.

CanadaReal Estate and Construction

In Alberta's fast-moving construction sector, disputes over payment delays and project performance can escalate quickly. A recent Alberta Court of Appeal decision in Tempo Alberta Electrical Contractors Co Ltd v Man-Shield (Alta) Construction Inc1 clarifies two key principles that often collide in construction litigation: equitable set-off and the clean hands doctrine.

For construction law practitioners, this case provides useful guidance for when equitable set-off can serve as a valid defence to summary judgment.

What was the dispute between Tempo and Man-Shield about?

Tempo Electrical Contractors Co Ltd. ("Tempo") was retained by Man-Shield (Alta) Construction ("Man-Shield") to perform electrical work under a subcontract valued at over $3 million related to the construction of a facility in Edmonton, Alberta.2 The project experienced a 45-week delay, and both parties alleged responsibility for the resulting costs.3 Tempo claimed $678,261 in unpaid amounts

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from