Enforceability Of Limitation Periods Embedded In Multi-tier Dispute Resolution Clauses – The Court Of Appeal For Ontario Takes A View

DWF
DWF
Contributor
DWF

DWF

DWF is the largest listed legal business in the world, with an award-winning reputation for client...

View firm profile
Explore more from DWF

The case concerns the interpretation of a standard form construction contract between the Minister of Transportation (MTO) and J&P Leveque Bros. Haulage Ltd.

CanadaReal Estate and Construction

The case concerns the interpretation of a standard form construction contract between the Minister of Transportation (MTO) and J&P Leveque Bros. Haulage Ltd. (Leveque) [2025 ONCA 573] for the rehabilitation of 27 kilometres of Highway 60. The contract included a multi-tier claims review and dispute resolution process, requiring a notice of protest and alternative dispute resolution (ADR) within two years of contract completion. However, the referee decision, which ruled against MTO, was released after the two-year period had expired, raising the question of whether the contractual limitation period applied in such circumstances.

Background

The decision, issued on August 1st, 2025, is relevant for commercial or construction agreements with multi-tier dispute resolution provisions. The clause in question contained a field, regional and provincial level review processes conducted by MOT with respect to request for clarification delivered to the