The recent decision of Urban Mechanical Contracting Ltd. et al v Zurich Insurance Company Ltd., 2022 ONCA 589 has sent waves through the construction industry.

CanadaReal Estate and Construction

The recent decision of Urban Mechanical Contracting Ltd. et al v Zurich Insurance Company Ltd., 2022 ONCA 589 ("Urban") has sent waves through the construction industry. In Urban, the Ontario Court of Appeal refused two applications seeking to overturn a lower court decision which permitted a bond issuer, as a matter of law, to rescind a bond agreement on the basis of fraudulent misrepresentations and collusion, even where doing so would affect the rights of innocent third parties claiming against the bonds. While the Urban decision addresses whether such relief could be available to a bond issuer, the decision itself is not a determination of whether Zurich Insurance Company Ltd. (the "Zurich") will, in fact, be entitled to rescind its bond agreements with Bondfield Construction Company Limited ("Bondfield") for the St. Michael's Hospital Redevelopment Project in Toronto, Ontario (the "Project").

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from