Court Of Appeal Overturns The Application Of A Contractual Limitation Period In A Construction Contract

The Ontario Court of Appeal's recent decision in Ontario (Transportation) v. J & P Leveque Bros. Haulage Ltd. (Leveque) overturned a lower court's ruling that a construction contract which had varied the basic statutory limitation period.

CanadaReal Estate and Construction

The Ontario Court of Appeal's recent decision in Ontario (Transportation) v. J & P Leveque Bros. Haulage Ltd. (Leveque)1 overturned a lower court's ruling that a construction contract which had varied the basic statutory limitation period barred the Ontario Minister of Transportation (MTO) from bringing a claim against J & P Leveque Bros. Haulage Ltd. (Leveque).

Background

Leveque concerned the interpretation of general conditions in a construction contract that set out a detailed claims review process. A party contesting the final step in the process — the referee decision — was required to file a notice of protest and engage in alternative dispute resolution (ADR) before commencing litigation. Although this process was to be done within two years of contract completion, the referee decision (which ruled against MTO) was not released until after the two-year contractual limitation period expired.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from