Court Clarifies Construction Act Transition Provisions: Date Of Prime Contract Is Key For Application Of Section 87.3

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

The changes to Ontario's construction lien legislation continue to make themselves felt with the Ontario Superior Court's recent decision in Crosslinx Transit Solutions Constructors v. Form & Build Supply (Toronto) Inc. (2021 ONSC 3396) ("Crosslinx").

CanadaReal Estate and Construction

The changes to Ontario's construction lien legislation continue to make themselves felt with the Ontario Superior Court's recent decision in Crosslinx Transit Solutions Constructors v. Form & Build Supply (Toronto) Inc. (2021 ONSC 3396) ("Crosslinx"), which interpreted the transition provisions of the Construction Act,  R.S.O. 1990, c. C.30. In the Crosslinx case, the Court concluded that the "contract" used to determine whether the old Construction Lien Act or the new Construction Act applies under section 87.3(1)(a) is the prime contract between the owner and the contractor. 

Background

On July 1, 2018, significant changes to Ontario's construction lien legislation came into force. Of particular note, and at issue in the Crosslinx case, section 31 of the Act was amended to increase the deadline to preserve a lien from 45 to 60 days and section 36 was amended to increase the timeline to perfect a lien from 45 days to 90 days. However, whether these amended

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from