Construction Liens And Adjudication Orders: The Court Weighs In On Having To "Pay Twice"

Blaney McMurtry LLP
Blaney McMurtry LLP
Contributor
Explore more from Blaney McMurtry LLP

From the moment the draft Adjudication provisions were presented to the construction industry, payors (owners mostly) made it clear they were very concerned about situations...

CanadaReal Estate and Construction

From the moment the draft Adjudication provisions were presented to the construction industry, payors (owners mostly) made it clear they were very concerned about situations where they may have to "pay twice", given that unpaid contractors and subcontractors are permitted to run lien claims and Adjudications simultaneously.

In the case of a construction lien, an owner may have to post the full amount of the claim, plus security for costs, into court to clear title. The owner could also end up having to pay an adjudicator's determination on an interim basis, while their dispute makes its way through the court system to (hopefully) obtain an order that they are not liable for the claim, and to recover the funds paid into court. In the meantime, they will have "paid twice"; once to satisfy the Adjudication Order, and a second time to post security with the court.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be ought about your specific circumstances.