Share on LinkedInShare on LinkedIn

ARTICLE · 23 DECEMBER 2022

Condo Corp 052 0580 (o/a The Tradition At Southbrook) v Carrington Holdings Ltd, 2022 ABKB 623: Alberta Court Of King's Bench Reaffirms Need To Combat Delayed Proceedings

McCarthy Tétrault
McCarthy Tétrault
Contributor
McCarthy Tétrault

McCarthy Tétrault

McCarthy Tétrault LLP provides a broad range of legal services, delivering strategic and...

View firm profile
Explore more from McCarthy Tétrault

Access to efficient dispute resolution is an increasing issue to businesses and other commercial parties. Conversely, inefficient dispute resolution by commercial parties is an increasing issue for Canadian courts.

CanadaReal Estate and Construction

Introduction

Access to efficient dispute resolution is an increasing issue to businesses and other commercial parties. Conversely, inefficient dispute resolution by commercial parties is an increasing issue for Canadian courts. A recent decision from the Alberta Court of King's Bench (the "Court") illustrates these tensions. In Condominium Corporation 052 0580 (o/a The Tradition at Southbrook) v Carrington Holdings Ltd, 2022 ABKB 623,[1] the Court dealt with applications by several defendants for dismissal for delay in a residential construction dispute. In the result, the Court reiterated that as Alberta courts commit to combat litigation delay, parties to a dispute that fail to meet their common law and statutory obligations to "proceed with proper expedition" must be prepared to face potential legal consequences, including dismissal of all or any part of a claim.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.