Concrete Consequences For Delay: Alberta Court Dismisses Residential Construction Defect Claim In Peters v Countryside Masonry

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

Construction claims often arise long after the events in question have taken place. That delay is sometimes unavoidable, as defects can take years to appear. Time is also lost to genuine attempts to resolve issues...

CanadaReal Estate and Construction

Construction claims often arise long after the events in question have taken place. That delay is sometimes unavoidable, as defects can take years to appear. Time is also lost to genuine attempts to resolve issues both before and after going to court.

In such cases, how do courts determine if an inordinate delay has occurred? In Peters v Countryside Masonry Inc. ("Countryside Masonry"), Justice N.E. Devlin of the Alberta Court of King's Bench (the "Court") dismissed a residential construction claim under Rule 4.31 of the Alberta Rules of Court, because very little substantial steps were taken over the eight-year period since the litigation was commenced.

This decision emphasizes the responsibility of parties to move litigation forward meaningfully. Failure to do so may lead to your claim being struck. In doing so, the Court underlines the importance of meaningful advancement, as opposed to periodic action which does little to advance the claim to trial or resolution.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from