Clear Statement Of Intent To Lien Is A Requirement When Delivering Notice Of Lien

The Trenchline case involved Trenchline as subcontractor, Unimac as general contractor and Metrolinx as owner.

CanadaReal Estate and Construction

In a decision released September 30, 2016, Master Wiebe has provided clarity with respect to the requirements for a valid Written Notice of Lien pursuant to section 24 of the Construction Lien Act (the "CLA").

Those familiar with section 24 of the CLA will know that it is a powerful tool for unpaid parties to use in holding up the flow of funds from an owner prior to taking the formal step of registering a construction lien.

Section 24 provides that a payer may pay a contractor or subcontractor up to 90 per cent of the price of services or materials supplied under that contract or subcontract unless, prior to making the payment, the payer has received a "written notice of a lien". Where the payer has received a written notice of a lien, they must retain an amount sufficient to satisfy that lien, in addition to the normal statutory holdback, before making further payment.