An issue that consistently arises in tendering disputes involves
an owner's right to forgive or waive a defect in a submitted
bid. In the recent decision of Maglio Installations Ltd. v. Castlegar (City),
2018 BCCA 80, the BC Court of Appeal addressed the general
legal principles underlying this complicated issue.
In February 2013, the City of Castlegar issued an invitation to
tender bids for the construction of a swimming area next to the
Columbia River. Several companies responded to the invitation,
including Marwest Industries Ltd. and Maglio Installations Ltd. The
invitation to tender required bidders to complete a preliminary
construction schedule ("PCS") and stated that time would
be of the essence in completing the project. The invitation to
tender also required bidders to confirm their ability to comply
with construction milestone dates. Due to various regulatory
approval and water level forecasting issues, the City revised the
milestone dates on several