In the recent decision of
Shelly Morris Business Services Ltd v Syncor Solutions
Limited,1 the Supreme Court of British
Columbia assessed whether a contractor has a valid builders lien
for pre-construction services in relation to a project where
construction ultimately never commenced due to the COVID-19
pandemic. The Court provides a helpful analysis of what constitutes
an "improvement" under the B.C. Builders Lien
Act ("BLA").2 This
bulletin summarizes the decision and the key takeaways for industry
participants.
Background
In May 2019, Shelly Morris Business Services Ltd.
("SMBS"), a tenant of two office
premises located in Vancouver and Richmond, B.C., contracted with
Syncor Solutions Limited ("Contractor")
to provide interior design and construction management services for
the renovation of the leased office space (the
"Project").3 The
Contractor started performing pre-construction activities such as
site visits, design work, and ordering of materials