Can a legal hypothec arise from plans and specifications drawn at a project's permitting and authorization stage, even when those plans are not used for the project's construction?

CanadaReal Estate and Construction

Executive summary

Can a legal hypothec arise from plans and specifications drawn at a project's permitting and authorization stage, even when those plans are not used for the project's construction? In a recent decision, the Quebec Court of Appeal held that an architectural firm could indeed validly create a legal hypothec of construction, even though the firm had contributed plans and specifications that were only used to obtain the necessary permissions for the transformation and renovation of a building.1

Background

In April 2015, a real estate developer (the "Developer") began a project to transform an old Outremont convent into a high-end residential complex.

The Developer mandated an architectural firm (the "Architects") to, among other things, secure residential zoning, produce a compliant implementation and integration plan, and assist the Developer in obtaining the approvals required from various decision-making authorities. The Architects

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from