BC Court Of Appeal Confirms: Subcontractors Still Have A Right To The Holdback, Even After Posting Security

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

The British Columbia Court of Appeal recently delivered a significant decision in Kingdom Langley Project Limited Partnership v. WQC Mechanical Ltd., 2025 BCCA 169 ("Kingdom Langley")...

CanadaReal Estate and Construction

The British Columbia Court of Appeal recently delivered a significant decision in Kingdom Langley Project Limited Partnership v. WQC Mechanical Ltd., 2025 BCCA 169 ("Kingdom Langley"), which has important implications for how builders liens are managed in the province. This ruling reaffirms the long-standing "dual lien" theory under British Columbia's Builders Lien Act ("BLA"), particularly regarding the interplay between liens against land and liens against holdback funds.

The case: A dispute over holdback release

The appeal in Kingdom Langley arose from a dispute between Kingdom Langley Project Limited Partnership ("Kingdom"), the project owner, and WQC Mechanical Ltd. ("WQC"), a subcontractor. WQC had a proven claim for a builders lien and sought the release of its proportionate share of the holdback retained by Kingdom under section 4 of the BLA.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from