Alberta Master Requires True Cost Estimate And Reaffirms Need For Appropriate Security In Builders’ Lien Applications

Blake, Cassels & Graydon LLP
Blake, Cassels & Graydon LLP
Contributor
Blake, Cassels & Graydon LLP

Blake, Cassels & Graydon LLP

As one of Canada’s top business law firms, Blake, Cassels & Graydon LLP (Blakes) provides...

View firm profile
Explore more from Blake, Cassels & Graydon LLP

The recent Alberta Master’s decision in Zahmol Properties Ltd. v. Richardson Bros. (Olds) Ltd. is the first reported analysis of section 48 of the Alberta Builders’ Lien Act (BLA), which section allows an owner to post security to discharge a lien from title.

CanadaReal Estate and Construction

Copyright 2011, Blake, Cassels & Graydon LLP

Originally published in Blakes Bulletin on Construction, April 2011

The recent Alberta Master's decision in Zahmol Properties Ltd. v. Richardson Bros. (Olds) Ltd. is the first reported analysis of section 48 of the Alberta Builders' Lien Act (BLA), which section allows an owner to post security to discharge a lien from title. The case confirmed the requirement that any such security must represent an adequate replacement for the land itself. Most significantly, Master Laycock rejected the usual practice of fixing the costs portion of the security in a builders' lien application at a further 10% to 15% of the sum to be posted and instead held that a "genuine calculation" of anticipated costs was required.