When Does The 45-Day Builders Lien Deadline Start In BC? Three Lessons From Cancon Construction

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP ("Miller Thomson") is a national business law firm with approximately 500...

View firm profile
Explore more from Miller Thomson

A recent British Columbia Supreme Court decision provides important guidance on one of the most common and consequential issues under the Builders Lien Act (the “BLA”): When does the 45-day period for filing a builder’s lien actually begin?

CanadaReal Estate and Construction

A recent British Columbia Supreme Court decision provides important guidance on one of the most common and consequential issues under the Builders Lien Act (the “BLA”): When does the 45-day period for filing a builder’s lien actually begin? In 1110486 B.C. Limited v. Cancon Construction Ltd., 2026 BCSC 1532 (“Cancon”), the Court considered three potential triggers for the lien filing period under section 20 of the BLA: issuance of a certificate of completion accompanied by the required statutory notice, completion of a head contract, and completion of the improvement itself. The decision serves as an important reminder that seemingly minor procedural missteps can have significant consequences for owners, contractors, subcontractors, and consultants alike.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from