Alberta Court Of Appeal Finds That Certificate Of Lis Pendens To Perfect Builders' Lien May Not Be Required

Blake, Cassels & Graydon LLP
Blake, Cassels & Graydon LLP
Contributor
Blake, Cassels & Graydon LLP

Blake, Cassels & Graydon LLP

As one of Canada’s top business law firms, Blake, Cassels & Graydon LLP (Blakes) provides...

View firm profile
Explore more from Blake, Cassels & Graydon LLP

The Court ruled that if an owner files an originating application in respect of a lien, the contractor may not be required to register a CLP, depending on the circumstances.

CanadaReal Estate and Construction

In a recent decision, TRG Developments Corp. v. Kee Installations Ltd. (TRG Developments), the Alberta Court of Appeal (Court) was required to determine whether the failure to register a certificate of lis pendens (CLP) within 180 days after registering a builders' lien means, in all circumstances, that the lien ceases to exist.

The Court ruled that if an owner files an originating application in respect of a lien, the contractor may not be required to register a CLP, depending on the circumstances.

CLP REGISTRATION REQUIREMENT

Section 43 of the Builders' Lien Act (Act) provides that a lien ceases to exist unless, within 180 days from registering the lien, the lien claimant commences an action to realize on the lien and registers a CLP. The CLP is intended to give the landowner notice of pending litigation in respect of the lien. The requirement to register a CLP in order to perfect a lien is mandatory under the Act.