If you are in the construction industry, you will have heard of
the "pay-when-paid" clause and its evil twin, the
"pay if paid" clause. Though widely used, these clauses
remain controversial and are often confused.
While both of these terms attempt to affect a general
contractor's obligations to subcontractors when the owner does
not pay that general contractor, they differ in important ways.
A "pay-when-paid" clause (i.e., that the general
contractor will pay the subcontractor within "X" days of
receiving payment from the owner) really only addresses the timing
of payments; it does not affect the underlying obligation to pay
for work performed.
On the other hand, a "pay-if-paid" clause (i.e. that
the general contractor only incurs an obligation to pay the
subcontractor if, and only if, it is first paid by the owner) may
constitute a condition precedent that excuses the general
contractor from having to pay the subcontractor if the owner does
not pay the general