ARTICLE · 26 APRIL 2017

Ontario Court Grants Injunction To Prevent Interference With Pipeline Maintenance Work: Enbridge Pipelines Inc. V. Williams And Hill , 2017 Onsc 1642, Ontario Superior Court Of Justice (Broad J.), 15 March 2017

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The Court rejected the defendants' argument that it must consider whether the duty to consult and accommodate had been fully discharged before granting an injunction to a private party.

CanadaGovernment, Public Sector

The Ontario Superior Court of Justice allowed an injunction application by Enbridge Pipelines Inc. to prohibit the Aboriginal defendants from interfering with its maintenance work on two pipelines in the Hamilton, Ontario area. The Court rejected the defendants' argument that it must consider whether the duty to consult and accommodate had been fully discharged before granting an injunction to a private party.

Enbridge owns and operates an interprovincial pipeline system extending across Canada and the USA. Line 10 is a 143-km long stretch of pipeline running between North Westover, Ontario to Buffalo, New York. Line 11 runs between Westover, Ontario and Nanticoke, Ontario. The easements for these pipelines had been granted to Enbridge's predecessor.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.