ARTICLE · 25 SEPTEMBER 2018

Meaningful Consultation Requires Grappling With Indigenous Concerns

On August 30, 2018, the Federal Court of Appeal (the Court) issued a decision that quashed the Governor-in-Council (GIC) ...

CanadaGovernment, Public Sector

On August 30, 2018, the Federal Court of Appeal (the Court) issued a decision that quashed the Governor-in-Council (GIC) approval for the Trans Mountain Expansion Project (the TMX). See Tseil-Waututh Nation v Canada (Attorney General) 2018 FCA 153. One of the reasons the approval was quashed was that the federal government failed to fulfill its duty to consult and accommodate Indigenous peoples potentially impacted by the TMX. The Court held that the government failed to "engage, dialogue meaningfully and grapple with the real issues raised by the Indigenous peoples so as to explore accommodation of those concerns" ( at para 6).

The Court's other ground for the quashing the approval was that the National Energy Board (NEB or Board) unjustifiably defined the scope of the project to exclude project-related tanker traffic such that the government could not rely on the NEB's report. We have already discussed the NEB's "critical error" in not including project-related

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from