On February 4, 2020, the Federal Court of Appeal (FCA) released
its decision in Coldwater First Nation v. Canada (Attorney
General), dismissing judicial review applications
challenging the federal Cabinet's approval of the Trans
Mountain Pipeline Expansion Project. The FCA found that there were
no legal grounds for setting aside Cabinet's decision.
This is the latest step in a long series of challenges to the
project.
In August 2018, the FCA quashed Cabinet's initial approval
of the pipeline in Tsleil-Waututh Nation et al. v. Attorney General
of Canada et al. (Tsleil-Waututh Nation). We
detailed the case in a previous article.
After the Tsleil-Waututh Nation decision, Canada
re-initiated the consultation process with potentially-affected
Indigenous peoples and also referred review of project-related
marine shipping back to the National Energy Board (NEB) for a more
exhaustive analysis.