On July 1, 2018, the first portions of the new Construction
Act (the "CA")1 came into
effect. Section 87.3 of the CA contains transition provisions that
state when the new or old version of the CA applies. However, in
our June 2018 bulletin,2 we noted that some of the
transition provisions were ambiguous or challenging to apply. The
absence of a definition for when the procurement process commences
or a right under section 39 to request the prime contract date were
particularly concerning.
The Ontario government has now remedied these and other
transition issues through the Restoring Trust, Transparency and
Accountability Act, 2018 (the "Restoring Trust
Act").3 The Restoring Trust Act received
royal assent on December 6, 2018 such that it is now law. As
described below, it contains several key amendments to clarify the
transition provisions in the CA. It also adds detail to
the adjudication and holdback sections in the CA.