Ontario Superior Court Provides Insight On The Legal Characterization Of Holdback Amounts Concerning A Project On First Nations Lands

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP (“Miller Thomson”) is a national business law firm with more than 550 lawyers...

View firm profile
Explore more from Miller Thomson

A recent decision of the Ontario Superior Court of Justice has provided useful insight into how a trust claim under the Construction Act, R.S.O. 1990 c. C.30 (the "Act") can be advanced...

CanadaFinance and Banking

Case commentary – Northwest Angle 33 First Nation. v. Razar Contracting Services Ltd.et al., 2023 ONSC 1233

A recent decision of the Ontario Superior Court of Justice has provided useful insight into how a trust claim under the Construction Act, R.S.O. 1990 c. C.30 (the "Act") can be advanced on First Nations lands and how statutory and contractual holdback amounts will be legally characterized by the court.

Facts

In February 2020, North West Angle 33 First Nation (the "First Nation") contracted with Razar Contracting Services Ltd.("Razar") for the construction of a water system to provide safe drinking water to the residents of the First Nation (the "Contract"). Pursuant to the terms of the Contract, the First Nation was required to retain a 10% statutory holdback and 2% maintenance holdback from progress payments made to Razar.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from