The Alberta Utilities Commission (AUC) announced it will hold
an inquiry "into the ongoing economic, orderly and efficient
development of electricity generation in Alberta". The inquiry
flows from the Alberta government's recent order in
council and regulation that paused approvals for new
renewable electricity generation projects until February,
2024.
The AUC has said the Inquiry "will include reviewing the
role of municipal governments in land selection for project
development and review." The role of municipal governments in
the siting of electricity generation projects and the AUC's
approval process is a subject of considerable debate in some parts
of Alberta.
Module A, the first phase of the Inquiry, will look at impacts
on land arising from electricity generation projects, including
siting and reclamation issues. There will be opportunities to
provide submissions this fall with an oral hearing to be held in
mid-December 2023. While the AUC has said more