This bulletin was updated on October 20, 2026.
This is the latest on the integration of repowered facilities in the second window of the Independent Electricity System Operator’s (IESO) Long-Term 2 (LT2) Request for Proposals (RFP) and Medium-Term 3 (MT3) RFP.
Eligibility
In late 2025, the IESO advised that repowered facilities would be ineligible to participate in the first window of the LT2 RFP (i.e., LT2(e-1) and (c-1)), but that steps would be taken to integrate participation by repowered facilities in the second window of the LT2 RFP (i.e., LT2(e-2) and (c-2)).
The IESO has since announced it will indeed be offering an LT2(e-2) and (c-2) RFP stream for repowered facilities with a cap of one terawatt (TW). This is in addition to the procurement targets for new-build facilities (3.6 terawatt-hours (TWh) energy and a minimum of 400 megawatts (MW) capacity), which will proceed by way of its own separate stream to ensure they remain competitive against the project development cost