Like it or not, a written contract constitutes the law between
the parties to that contract. If one party does not follow
the terms of the contract, especially in critical situations like
the termination of the contract, changes to the scope of work,
deficiencies, or delay claims, that party may find itself unable to
claim for damages against the other party.
In an Ontario case, Urban Mechanical v. University of
Western Ontario, 2018 ONSC 1888, a subcontractor failed to
deliver a "notice of dispute" under the subcontract
relating to a decision made by the general contractor. The
subcontract provided that the subcontractor was deemed to accept a
decision of the general contractor and to have waived and released
the general contractor from any claims in respect of that decision
unless, within seven working days after receipt of the general
contractor's decision, the subcontractor sent the general
contractor a "notice of dispute" in writing.