Like it or not, the contract constitutes the law between the
parties that contract. It sets out the rights and obligations
between the parties. If one party does not follow the terms in the
contract, especially in situations involving the termination of the
contract, changes to the scope, correction of deficiencies, or
dispute resolution, that party may find it is unable to make a
claim against the other party.
In a recent case, Urban Mechanical v. University of Western
Ontario, 2018 ONSC 1888, a subcontractor failed to deliver a
"notice of dispute" under the subcontract relating to a
decision made by the contractor. The subcontract provided that the
subcontractor was deemed to accept a decision of the general
contractor and to have waived and released the general contractor
from any claims in respect of that decision unless, within seven
working days after receipt of the general contractor's
decision, the subcontractor sent the contractor a notice of dispute
in