In C.M. Callow Inc. v. Zollinger, 2020 SCC 45,
the Supreme Court of Canada clarified the scope of the duty of good
faith in the performance of contracts.
This dispute arose from a contract for winter maintenance
services between the contractor and a condo complex. The contract
between them allowed the condo complex to terminate the services if
it was unsatisfied or no longer needed the services. In early 2013,
the condo complex decided it would not continue its contract with
the plaintiff for the following winter, but it did not advise the
plaintiff. The plaintiff continued to provide services for the
complex, some at no cost, in the belief that the condo complex was
satisfied with its services and would renew the contract. In
September 2013, the complex finally advised the plaintiff that it
had no intention of continuing the services. The plaintiff sued for
breach of contract.