If an approval is not yet implemented, a new application may take advantage of the capped infrastructure charges regime.

AustraliaReal Estate and Construction

In this alert, Partner David Nicholls and Law Graduate Ruby Rayner discuss a recent judgment of the Queensland Court of Appeal which confirms that where an approval exists that has not been implemented a new application may be made for development to take advantage of the capped infrastructure charges regime.

In Gladstone Regional Council v Homes R Us (Australia) Pty Ltd [2015] QCA 175, the Court confirmed the bounded nature of code assessment and the absence of residual discretion to refuse compliant applications in response to arguments by the Council that it had discretion to refuse a second application for reconfiguration of land (ROL) which was made to take advantage of capped infrastructure charges that were lower than those payable under a condition imposed on an earlier development approval. No basis for refusal was asserted other than the fact that an earlier ROL for the project had been approved and that approved operational work had been undertaken.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from