Share on LinkedInShare on LinkedIn

ARTICLE · 09 FEBRUARY 2012

Western Australian Supreme Court finds compulsory acquisition notices invalid

Agencies in WA must ensure compliance with all procedural aspects of land acquisition legislation when acquiring land.

AustraliaReal Estate and Construction

Key Points:

Agencies taking land under compulsory acquisition legislation should ensure that they include a detailed description of the land they intend to resume in order to ensure that persons who have or may have an interest in the land are able to engage in the objection process fully informed.

A recent decision of the Western Australian Supreme Court shows that it is critical for agencies to ensure that they properly comply with all procedural aspects of land acquisition legislation when seeking to compulsorily acquire land.

In McKenzie v Minister for Lands [2011] WASC 335 (6 December 2011), Chief Justice Martin found that three notices of intention to take land (notices) did not contain information which would enable the boundaries of the land intended to be acquired to be identified. As a consequence, the Court found that the notices did not comply with the Land Acquisition Act 1977 (WA) and were invalid.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from