WA Supreme Court ensures liquidators of insolvent construction contractors give as good as they get: Hamersley iron Pty Ltd v James [2015] WASC 10

The case demonstrated conflict of payment rights in construction contracts in the context of the contractor's insolvency.

AustraliaReal Estate and Construction

In construction contracts, payment rights often conflict and compete with each other for priority. Never is this truer than in the context of a contractor's insolvency or an adjudication application under security of payment legislation.

This was the case in Hamersley Iron Pty Ltd v James [2015] WASC 10.

In that case, Hamersley had instructed a construction contractor, Forge Group Construction Pty Ltd, to design and construct fuel hubs. Forge started work on the hubs but was placed into liquidation without having ever finished the job. In the meantime, Forge applied for adjudication of its payment claims, which Hamersley had disputed, and the adjudicator awarded Forge just over $700,000 under its contract with Hamersley.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from