Undocumented variations and the Home Building Act (NSW): Clarity and a ray of hope for builders

Edwards’ Case & payment for construction work not expressly set out in building contract or written variation order.

AustraliaReal Estate and Construction

Edwards v Sydney Building Group Pty Ltd [2011] NSWCA 154

A decision handed down by the Court of Appeal on 23 June 2011 in Sydney Building Group v Edwards (Edwards' Case) has provided clarity and a ray of hope for residential builders in NSW seeking payment for construction work not expressly set out in the building contract or a written variation order.

Background

The Home Building Act 1989 (NSW) (HBA) contains strict documentary obligations often resulting in builders finding it difficult or seemingly impossible to recover payment for works which are not agreed in writing[1].

In Edwards' case, in which the builder was represented by Gadens Lawyers, the Edwards and the Builder entered into a standard contract for the construction of a home at Avalon, on the stunning Northern Beaches (Contract).  As construction progressed the Edwards directed that soil be removed from the site (Soil Works).  There was no provision in the Contract for the Soil Works.