Time limits in building work contracts – which one applies?

Duncan v Bert Farina Constructions offers important insights into how these time limitations apply.

AustraliaReal Estate and Construction

Navigating the complexities of time limits in building work contracts is crucial for both homeowners and builders. The recent case of Duncan v Bert Farina Constructions Pty Ltd [2024] SASCA 67 before the South Australian Court of Appeal offers important insights into how these time limitations apply.

Case study – Duncan v Bert Farina Constructions Pty Ltd

In this case, the South Australian Court of Appeal considered competing time limitation provisions in the Building Work Contractors Act 1995 (SA) (BWCA) and the Development Act 1993 (SA) (DA), with the judgment turning on the analysis of the purpose and power given by those provisions.

Case background

In June 2016, Mr Duncan and Ms Roberts purchased a house on which Bert Farina Constructions had been contracted to perform residential building work. The builder asserted that the work reached practical completion in December 2015.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from