The High Court decides – Do you need a valid reference date for a payment claim under Security of Payment legislation?

The High Court unanimously held that a reference date is essential to the validity of a payment claim made under the Act.

AustraliaReal Estate and Construction
Craig Tanzer
Craig Tanzer

Is it imperative to have a valid reference date for a payment claim made under Security of Payment Legislation? The High Court determines the importance and effect of reference dates once and for all in Lewence Construction Pty Ltd v Southern Han Breakfast Point Pty Ltd [2016] HCA 52

Summary

Today the High Court handed down its first ever decision concerning security of payment legislation in Australia (Lewence Construction Pty Ltd v Southern Han Breakfast Point Pty Ltd [2016] HCA 52). The High Court affirmed the view that a valid reference date is essential to a claimant's right to recover payment under security of payment legislation.

This decision will have far reaching consequences for the building and construction industry, as it clarifies the recent confusion regarding whether a payment claim will be automatically invalid if it is not made in relation to a valid reference date.