The New South Wales Government has continued its drive to
tighten laws regarding construction work in the state. Hot on the
heels of changes to the security of payment regime, the Home
Building Act has been amended, ostensibly with a view to clamping
down on unlicensed and uninsured contracting. Some of the changes
go further and are worthy of close scrutiny.
Significant changes have been made to the laws in New South
Wales regarding home building work. The changes are a mixed bag for
contractors doing home building work as well as for those who
engage them.
In June 2014, the Home Building Amendment Act 2014 was
passed, which foreshadowed wide-ranging changes to the Home
Building Act 1989. The changes come into force in three
phases, the first of which took effect from 31 December 2014
and the second of which took effect from 15 January 2015. The third
phase will come into effect from 1 March 2015.