Amendments to the Building and Construction Industry Payment Act
timeframes and procedures commence TODAY, 15
December 2014.
The amended Act applies to existing
contracts.
Last-minute changes to the transitional arrangements mean that
the amended timeframes and procedures will now apply to
BCIPA payment claims made in connection with existing
contracts.
When the amending legislation was originally passed, the new
regime was to apply only to contracts entered into after the
commencement date.
How these changes affect your existing construction
contracts
The amended timeframes and procedures apply to existing
contracts in the following way:
- if a payment claim has been made before the
commencement date and there are outstanding steps relating to that
claim (eg. payment schedule, referral to adjudication, adjudication
response etc), the timeframes of the unamended Act will apply to
those outstanding steps; and