Superintendent: An Agent Or Independent Of The Principal?

This case concerns a development of five separate buildings comprising commercial suites and residential apartments. V601 was the developer.

AustraliaReal Estate and Construction

Case Note on V601 v Probuild [2021] VSC 8491

Background

This case concerns a development of five separate buildings comprising commercial suites and residential apartments. V601 was the developer. V601 engaged Probuild to design and construct the project under an amended contract form of AS4902-2000 (Contract).

Issues

The issues concerned time-related disputes. V601 had claimed liquidated damages while Probuild claimed damages (comprising bonuses, delay damages, acceleration costs & variations) and Extension of Time (EOT). In this article, we focus on Probuild's challenge to the independence of the Superintendent in assessing Probuild's EOT claims.

Function and Role of Superintendent

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from