Recent Victorian Supreme Court case casts doubt on enforceability of contract provisions seeking to impose a time limit on statutory claims

This was contrary to certain decisions in NSW, where limits on statutory remedies under the ACL were held enforceable.

AustraliaReal Estate and Construction

Introduction

On 17 May 2018, in the case of Brighton Australia Pty Ltd v Multiplex Constructions Pty Ltd [2018] VSC 246 (Brighton v Multiplex), Justice Riordan held that subcontract provisions which purported to impose a time limitation for commencing an action of misleading or deceptive conduct under the Australian Consumer Law (ACL) which was less than the 6 year time period provided by s 236(2) of the ACL, were unenforceable, on the basis that such a purported limitation was contrary to public policy.

This is in contrast to certain decisions of the Supreme Court of New South Wales, which have found that monetary or temporal limits on statutory remedies under the ACL are enforceable, because they can be distinguished from a complete bar to, or purported ouster of, statutory remedies.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from