Queensland public holidays and compliance with time limits under the Building and Construction Industry Payments Act (BCIPA)

To ensure compliance with the strict time limits under the BCIPA, always consider all possible relevant public holidays.

AustraliaReal Estate and Construction

In brief - Always consider public holidays when calculating time limits

To ensure compliance with BCIPA, claimants and respondents should consider all possible relevant public holidays - regardless of region - when calculating time limits for making and responding to claims and adjudication applications.

Different regional holidays can cause confusion and uncertainty

The Building and Construction Industry Payments Act 2004 imposes strict time limits for making and responding to payment claims and adjudication applications. Failure to comply with these time limits can have serious consequences for both claimants and respondents.

The time limits are measured in "business days", which naturally do not include public holidays.