Quantum meruit in the building and construction industry: Roude v Helwani [2020] NSWCA 310

A quantum meruit claim can occur in building and construction matters if there is no contractual basis to claim payment.

AustraliaReal Estate and Construction

The recent decision of Roude v Helwani (' Roude ') by the New South Wales Court of Appeal concerned a builder's claim for payment on a quantum meruit basis and the requirements for establishing that cause of action, specifically whether the builder was required to lead evidence of the market rate for the work performed.

Quantum meruit is a Latin term meaning 'what one has earned' which roughly translates to the 'reasonable value of services'. A claim for quantum meruit often occurs in building and construction matters where there is no contractual basis to claim payment (or there is an issue with the contract). The builder may, for example, have performed work but did not accrue a right to payment under the contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from