ARTICLE · 13 JUNE 2018

Planning and Environment Court has discretionary power to grant an extension to the currency period under section 388 of the Sustainable Planning Act 2009 (SPA)

This matter is one of discretion to be exercised in the facts of each case having regard to the specified considerations.

AustraliaReal Estate and Construction

In brief

The case of Lake Maroona Pty Ltd v Gladstone Regional Council [2017] QPEC 25 involved an appeal against the Council's decision to refuse an application under section 383 of the Sustainable Planning Act 2009 (SPA) for an extension of a currency period for a development approval for a multi-unit residential development.

Extending the period for a development approval

The case was decided under the SPA. Relevantly the assessment manager was to have regard to the matters under section 388 of the SPA when considering whether an extension under section 383 of the SPA should be granted. The Court determined that the test in Mantle v Sunshine Coast Regional Council [2015] QPEC 30 is to be applied when determining matters under section 388 of the SPA. In that case, it was held that the matters under section 388 of the SPA are to be considered but do not form preconditions to an approval. Hence, the matter is one of discretion which is to be exercised in