Performance penalties: Delays foreseeable? Metrolink Victoria Pty Ltd v Inglis [2009] VSCA 227

Are performance penalties payable by a tram operator due to significant delays to the tram network a reasonably foreseeable loss arising from a motor vehicle collision with a tram?

AustraliaReal Estate and Construction

Are performance penalties payable by a tram operator due to significant delays to the tram network a reasonably foreseeable loss arising from a motor vehicle collision with a tram?

Facts

This case will shape the future application of the test of reasonable foreseeability as it has redefined the range of losses recoverable from wrongdoers.

Metrolink owned trams on the Melbourne network. Inglis was the driver of a motor vehicle that collided with one of Metrolink's trams.

The collision resulted in damage to a tram and significant delays to the tram network. Prior to the commencement of proceedings, Inglis admitted negligence and paid for the costs of repairing the damaged tram. Inglis denied liability and refused to pay for the contractual losses sustained by Metrolink on the basis that they were not reasonably foreseeable and therefore too remote at law. Metrolink commenced proceedings to recover these losses.