ARTICLE · 01 DECEMBER 2021

Payment Claim served a day late leaves claimant more than a buck short

Recent case guides the interpretation of key terms relating to service under s31 Security of Payment Act (NSW).

AustraliaReal Estate and Construction

The Supreme Court of NSW recently dismissed a $6M+ adjudication application after finding that the claimant's Payment Claims were made a day later than the date they were physically provided to the respondent.

The decision provides important guidance for the interpretation of key terms relating to service under section 31 of the Security of Payment Act (NSW), and shows the potentially serious consequences of taking actions based on a miscalculated date of service.

Background

At 5.15pm on 3 February 2021, an employee of MGW Engineering Pty Ltd t/a Forefront Services (Forefront) delivered four Payment Claims to an employee of CMOC Mining Pty Ltd (CMOC). The four Payment Claims related to separate contracts and totalled over $6 million. CMOC served its Payment Schedules in response 11 days later on 18 February 2021