Owner of land is responsible for infrastructure charges related to a development approval even where they are not the applicant

This case concerns a land owner's liability to pay unpaid infrastructure charges related to a development approval.

AustraliaReal Estate and Construction

IN BRIEF

The case of Trevorrow v Council of the City of the Gold Coast [2017] QSC 12 is significant as it concerns a land owner's liability to pay unpaid infrastructure charges related to a development approval even where they are not the applicant for the development approval.

The case concerned the interpretation of section 639 of the Sustainable Planning Act 2009 prior to the amendments on 4 July 2014. However, the authors note that the current section 664 of the Sustainable Planning Act 2009 is in substantially the same terms and, in our view, would attract the same result.

Trevorrow brought an application in the Supreme Court of Queensland seeking declarations that the registered proprietor of land is not liable to the Council for an infrastructure charge under an infrastructure charges notice given with a decision notice for a development approval in circumstances where the registered proprietor was not the applicant for the development approval.